ChronoSphere Deployment

Visual roadmap for B7 & QA system implementation

SKAI Platform 2025 Timeline
Phase 0

Alignment & Setup

Conduct user interviews and workshops, setup Azure DevOps, backlog, boards, and governance structure.

This Week
0
Foundation
Phase 1

Design & Prototyping

Create design specifications (DS), functional specifications (FS), and configuration specifications (CfS).

4 Weeks
  • Create Design Specifications (DS)
  • Develop Functional Specifications (FS)
  • Define Configuration Specifications (CfS)
  • Architecture diagrams and wireframes
  • Weekly stakeholder checkpoints
  • 2-3 design iterations per module
1
Blueprint

Front-End Path

Front-End Activities
  • User interviews (B7 & QA users)
  • UI mock-ups & iterations
  • Clickable prototypes
  • UI deployment on SKAI DEV

Back-End Path

Back-End Activities
  • Confirm technical requirements (CfS)
  • Build & test chatbot logic on Streamlit
  • Connect to Snowflake tables
  • Manage prompt/context files
  • Deploy to SKAI DEV
Phase 2

Development & Testing

Proceed in 2-week sprints per module with multiple cycles until acceptance criteria are met.

6-8 Weeks
2
Build

SKAI Deployments

Deployment Activities
  • SKAI DEV build (front-end + back-end)
  • SKAI ACC build + internal testing
  • UAT on SKAI ACC with key users
  • Gradual rollout to PROD
  • MVP go-live
Phase 3

Pilot Deployment

Roll out first functional module to identify and fix issues, refine workflows with key user group.

4 Weeks
3
Validation
Phase 4

Gradual Rollout & UAT

Introduce subsequent modules from ACC to PROD with user acceptance testing (UAT) and sign off.

2 Weeks per module
4
Launch
Phase 5

Maintenance

Ongoing support and maintenance once all modules are validated in production.

Ongoing
5
Support